Which of the following pairs is correctly matched?


Definitions:

Material Requirements Plans

A planning and inventory control system used to manage manufacturing processes by determining material requirements and schedules.

Planned Order Releases

Instructions to start the manufacture, ordering, or delivery of items in a specific period, in accordance with the production schedule.

Projected Output Rate

The estimated rate at which a system or process is expected to produce goods or complete tasks over a specific period.

Inventory Holding Costs

The expenses associated with storing unsold goods, including costs related to warehousing, insurance, depreciation, and opportunity cost.