​Given the Below PERT/CPM Chart,how Many Days Does It Take

question 31

Multiple Choice

​Given the below PERT/CPM chart,how many days does it take for the project to end?
​Given the below PERT/CPM chart,how many days does it take for the project to end?   A) 15 days B) ​13 days C) ​12 days D) ​9 days