Activity a Has a Standard Cost of $500 and the Standard

question 48

Multiple Choice

Activity A has a standard cost of $500 and the standard time to complete Activity A is 5 weeks.The crash time for Activity A is 3 weeks and the crash cost is $600.What is the crash cost per week for Activity A?