Examlex

Solved

If an Activity's Optimistic Time Is 4 Days,its Realistic Time

question 58

True/False

If an activity's optimistic time is 4 days,its realistic time is 10 days,and its pessimistic time is 25 days,then its estimated time would be 11.5 days.