Construct a Network Diagram Using the Following Data

question 153

Essay

Construct a network diagram using the following data.For each activity,identify its early start time,late start time,early finish time,late finish time,and slack.Identify the critical path.
Construct a network diagram using the following data.For each activity,identify its early start time,late start time,early finish time,late finish time,and slack.Identify the critical path.


Definitions:

Training Hours

The total time spent in training activities, usually measured in hours, aimed at skill improvement or acquisition.

ISD Model

Instructional Systems Design model, a systematic approach to creating effective, efficient, and appealing educational programs and materials.

ADDIE Model

A systematic instructional design framework consisting of five phases: Analysis, Design, Development, Implementation, and Evaluation, used to develop educational and training programs.

Training Legislation

Laws and regulations that govern the requirements and standards for workplace training.

Related Questions