Consider the Following Program Evaluation Review Technique (PERT) Network A) E → F → H → I
B) B

question 98

Multiple Choice

Consider the following Program Evaluation Review Technique (PERT) network. The activities and their respective durations are given in the following table.
Which of the following paths of the given network is the critical path?
 Consider the following Program Evaluation Review Technique (PERT)  network. The activities and their respective durations are given in the following table. Which of the following paths of the given network is the critical path?    \begin{array}{|l|l|} \hline {\text { Activity }} &{\text { Duration(days)  }} \\ \hline \mathrm{A} & 5 \\ \hline \mathrm{B} & 7 \\ \hline \mathrm{C} & 15 \\ \hline \mathrm{D} & 10 \\ \hline \mathrm{E} & 13 \\ \hline \mathrm{F} & 9 \\ \hline \mathrm{G} & 6 \\ \hline \mathrm{H} & 10 \\ \hline \mathrm{I} & 11 \\ \hline \end{array}  A)  E → F → H → I B)  B → D → G → I C)  B → D → F → H → I D)  A → C → F → H → I
 Activity  Duration(days)  A5B7C15D10E13F9G6H10I11\begin{array}{|l|l|}\hline {\text { Activity }} &{\text { Duration(days) }} \\\hline \mathrm{A} & 5 \\\hline \mathrm{B} & 7 \\\hline \mathrm{C} & 15 \\\hline \mathrm{D} & 10 \\\hline \mathrm{E} & 13 \\\hline \mathrm{F} & 9 \\\hline \mathrm{G} & 6 \\\hline \mathrm{H} & 10 \\\hline \mathrm{I} & 11 \\\hline\end{array}


Definitions:

Jury Trial

A legal proceeding in which a jury makes a decision or findings of fact, which then direct the actions of a judge.

Foreclosure

The right of a mortgagee to apply to a court to have property sold when the mortgagor defaults or fails to perform some agreement in the mortgage.

Junior Mortgage

A mortgage subject to a prior mortgage.

Adjustable-Rate Mortgage

A mortgage loan with an interest rate that can fluctuate over time based on changes in a corresponding financial index that's attached to the loan.

Related Questions