A Project Has Three Possible Paths from Start to Finish

question 20

Multiple Choice

A project has three possible paths from start to finish. Path A-B-C is 15 hours; path A-C-D is 10 hours, and path A-C-E is 20 hours. Which one of the following statements is true?