Which of the Following Is the Critical Path for the Project

question 64

Multiple Choice

Which of the following is the critical path for the project network shown in the following diagram? Which of the following is the critical path for the project network shown in the following diagram?   A)  ACEF B)  ACDF C)  ABDF D)  ABCDEF