Optimistic Time
The shortest amount of time in which a task or project phase can realistically be completed, assuming everything proceeds better than is normally expected.
Crash Duration
The minimum time period needed to complete an activity or project phase by allocating the maximum resources.
Crash Cost
The additional costs associated with rushing or compressing a project schedule to complete it in the shortest time possible.
CPM Network
Critical Path Method Network, a project management tool that helps in determining the longest path of planned tasks to the end of a project.
Q8: Normalized tables eliminate _.<br>A) data dependency<br>B) data
Q8: What are the different categories of application
Q18: If an organization wants to own any
Q23: Virtual meetings can be synchronous or asynchronous.
Q26: Which of the following is a valid
Q61: The conversion of the existing traditional databases
Q71: In a database,columns that are keys of
Q79: Organizations analyze the structure of their industry
Q86: What is clickstream data?
Q86: According to the business process modeling notation