In an Activity Network Diagram, Slack Time = Late Finish

question 28

True/False

In an activity network diagram, slack time = late finish - early finish.


Definitions:

Cost Behaviour

The way in which costs change in relation to alterations in an organization's level of activity.

Relevant Range

The range of activity within which the assumptions about fixed costs and variable cost behavior hold true.

Production

The process of creating goods and services through the combination of human labor, materials, and technology.

Cost Estimation

The process of forecasting the costs associated with a project or production, taking into consideration all relevant variables.