What would be the estimated time for completion if the time estimates for report design are as follows? optimistic = 3 weeks; pessimistic = 9 weeks; realistic = 6 weeks


Definitions:

Negotiations

The act of discussing and arriving at a mutual agreement between parties with different interests or desires.

High-Context Culture

A culture in which communication relies heavily on implicit cues and contexts, with less explicit verbal information.

Low-Context Culture

A low-context culture is one in which communication is explicit, meaning is derived from the actual words spoken or written, and less is conveyed through nonverbal cues or context.

Communication Process

The sequence of steps through which information is transmitted and received between individuals or entities.