The Critical Path for the Network Activities Shown Below Is

question 106

Multiple Choice

The critical path for the network activities shown below is __________ with duration __________.  Activity  Duration  Immediate  Predecessors  A 10 B 8 C 2 A D 4 A E 5 B,C,D\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Duration } & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} \\\hline \text { A } & 10 & - - \\\hline \text { B } & 8 & - - \\\hline \text { C } & 2 & \mathrm {~A} \\\hline \text { D } & 4 & \mathrm {~A} \\\hline \text { E } & 5 & \mathrm {~B} , \mathrm { C } , \mathrm { D } \\\hline\end{array}


Definitions:

Process Conflict

Disagreements or disputes among team members about the logistics, delegation, and management of work tasks, often arising from differences in working styles or priorities.

Indirect Influence

is a form of power or persuasion where changes in attitudes, opinions, or behaviors are achieved not through direct persuasion but via secondary or subtler mechanisms.

Team Project

A task or assignment carried out by a group of individuals working together, leveraging their collective skills and knowledge to achieve a shared objective.

Relationship Conflict

refers to disagreements and personal incompatibilities between individuals, often causing tension and affecting morale.

Related Questions