The network below represents a project being analyzed by Critical Path Methods. Activity durations are A=5, B=2, C=12, D=3, E=5, F=1, G=7, H=2, I=10, and J=6.
a. What task must be on the critical path, regardless of activity durations?
b. What is the duration of path A-B-E-H-J?
c. What is the critical path of this network?
d. What is the length of the critical path?
e. What is slack time at activity H?
f. What is the Late Finish of activity H?
g. If activity C were delayed by two time units, what would happen to the project duration?
Inhibit
To restrain or hold back an action, process, or expression, often by regulation or external constraint.
Independent Person
An individual characterized by self-reliance and autonomy in thoughts and actions, often prioritizing personal goals over group objectives.
Citizen Of Turkey
An individual who is legally recognized as a national of the Republic of Turkey, either by birth or naturalization.
Obligated
The condition of being morally or legally bound to do something, carrying a sense of duty or requirement.
Q19: A crew of mechanics at the Highway
Q25: How might the transportation method be used
Q26: Suppose that the shadow price for assembly
Q30: Porter's Five Forces Model is used to
Q60: In the logarithmic approach to learning curve
Q73: The _ strategy describes a condition in
Q93: How has Franz Colruyt achieved low-cost leadership?<br>
Q110: How do goods and services differ with
Q115: Which of the following OM Strategy/Issues should
Q132: Which of the following is an example