A network consists of the following list. Times are given in weeks.
 Activity  Preceding  Duration  A 9 B  A 2 C  A 12 D  A 5 E  B 6 F  B 8 G  C, F 3 H  D 2 I  H 8 J  G, I 6 K  E, J 2\begin{array}{|c|c|c|}\hline \text { Activity } & \text { Preceding } & \text { Duration } \\\hline \text { A } & -- & 9 \\\hline \text { B } & \text { A } & 2 \\\hline \text { C } & \text { A } & 12 \\\hline \text { D } & \text { A } & 5 \\\hline \text { E } & \text { B } & 6 \\\hline \text { F } & \text { B } & 8 \\\hline \text { G } & \text { C, F } & 3 \\\hline \text { H } & \text { D } & 2 \\\hline \text { I } & \text { H } & 8 \\\hline \text { J } & \text { G, I } & 6 \\\hline \text { K } & \text { E, J } & 2 \\\hline\end{array}
a. Draw the network diagram.
b. Which activities form the critical path?
c. How much slack exists at activities A and F?
d. What is the duration of the critical path?


Definitions:

Innocent Purchaser

An individual who buys property without knowledge of any existing claims, disputes, or defects associated with it.

Fraud

An intentional deception made for personal gain or to damage another individual.

Sale-Or-Return Contract

A contract in which the buyer and seller agree that the buyer may return the goods at a later time.

Voidable Title

Title that occurs when a contract between the original parties would be void but the goods have already been sold to a third party.

Related Questions