Three Critical Path Activities Are Candidates for Crashing on a CPM

question 52

Essay

Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.
 Activity  Normal Time  Normal Cost  Crash  Duration  Crash Cost  A 9 days $8,0007 days $12,000 B 5 days $2,0003 days $10,000 C 12 days $9,00011 days $12,000\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \text { Normal Time } & \text { Normal Cost } & \begin{array} { c } \text { Crash } \\\text { Duration }\end{array} & \text { Crash Cost } \\\hline \text { A } & 9 \text { days } & \$ 8,000 & 7 \text { days } & \$ 12,000 \\\hline \text { B } & 5 \text { days } & \$ 2,000 & 3 \text { days } & \$ 10,000 \\\hline \text { C } & 12 \text { days } & \$ 9,000 & 11 \text { days } & \$ 12,000 \\\hline\end{array}
a. What is the crash cost per unit time for activity A?
b. What is the crash cost per unit time for activity B?
c. Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
d. Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?
e. Assuming no other paths become critical, how much can this project be shortened at what total added cost?


Definitions:

Human Dignity

The inherent worth of all individuals regardless of status, ensuring they are treated with respect and fairness.

Cultural Relativism

The idea that to truly grasp the beliefs and actions of a person, one must interpret them within the context of that person's specific cultural background.

Ethical Standards

The principles of right conduct guiding what people consider to be morally good or bad in their behavior and decision-making.

National Boundaries

Geographical borders that define the territorial limits of a country, affecting its governance, economy, and international relations.

Related Questions