Draw the AOA and AON Networks for the Following Project

question 23

Essay

Draw the AOA and AON networks for the following project and calculate the minimum project duration.
 Activity  Duration  (days)  Immediate  Predecessors  A 10 B 8 C 2 A D 4 A E 5 B,C,D\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Duration } \\\text { (days) }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} \\\hline \text { A } & 10 & - - \\\hline \text { B } & 8 & - - \\\hline \text { C } & 2 & \mathrm {~A} \\\hline \text { D } & 4 & \mathrm {~A} \\\hline \text { E } & 5 & \mathrm {~B} , \mathrm { C } , \mathrm { D } \\\hline\end{array}


Definitions:

Variable Costs

Costs that vary directly with the level of production or volume of output.

Present Value

The current worth of a future sum of money or stream of cash flows, given a specified rate of return.

Interest Rates

The cost of borrowing money, typically expressed as a percentage of the total amount loaned, paid to the lender over a specific period of time.

Capacity Alternatives

Options or strategies an organization can employ to adjust its capacity to meet changing demand.

Related Questions