A Simple CPM Network Has Three Activities, D, E, and F

question 45

Multiple Choice

A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=8.