Three Critical Path Activities Are Candidates for Crashing on a CPM

question 52

Essay

Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.
 Activity  Normal Time  Normal Cost  Crash  Duration  Crash Cost  A 9 days $8,0007 days $12,000 B 5 days $2,0003 days $10,000 C 12 days $9,00011 days $12,000\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \text { Normal Time } & \text { Normal Cost } & \begin{array} { c } \text { Crash } \\\text { Duration }\end{array} & \text { Crash Cost } \\\hline \text { A } & 9 \text { days } & \$ 8,000 & 7 \text { days } & \$ 12,000 \\\hline \text { B } & 5 \text { days } & \$ 2,000 & 3 \text { days } & \$ 10,000 \\\hline \text { C } & 12 \text { days } & \$ 9,000 & 11 \text { days } & \$ 12,000 \\\hline\end{array}
a. What is the crash cost per unit time for activity A?
b. What is the crash cost per unit time for activity B?
c. Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
d. Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?
e. Assuming no other paths become critical, how much can this project be shortened at what total added cost?


Definitions:

Health-Care Power of Attorney

A legal document allowing an individual to appoint someone else to make medical decisions on their behalf if they become incapacitated.

Constructive Trust

A remedy imposed by a court recognizing a person’s right to ownership of property because of fairness, even though legal title is held by someone else.

Living Will

A living will is a legal document that outlines an individual's wishes regarding medical treatment in circumstances where they are unable to communicate those desires themselves.

Advance Health Directive

A legal document specifying a person's preferences for medical treatment in situations where they might be unable to make decisions for themselves.

Related Questions