Examlex

Solved

Consider the Network Presented in the Following Table

question 25

Essay

Consider the network presented in the following table. Calculate
a. All possible paths
b. The critical path
c. The slack available at any non-critical points
d. The minimum project duration
 Task  Duration  (Days)  Immediate  Predecessors  A 5 None  B 3 A  C 4 A  D 2 C  E 1 B,D \begin{array}{|c|c|c|}\hline\text { Task } & \begin{array}{c}\text { Duration } \\\text { (Days) }\end{array} & \begin{array}{c}\text { Immediate } \\\text { Predecessors }\end{array} \\\hline \text { A } & 5 & \text { None } \\\hline \text { B } & 3 & \text { A } \\\hline \text { C } & 4 & \text { A } \\\hline \text { D } & 2 & \text { C } \\\hline \text { E } & 1 & \text { B,D } \\\hline\end{array}


Definitions:

Borderless Basis

Describes an approach or system that operates without the limitations or barriers imposed by geographic or political boundaries.

Conflict Minerals

Minerals sourced in areas of armed conflict, particularly the Democratic Republic of Congo and surrounding region, whose sale finances armed groups that perpetuate violence.

Armed Violence

The use of weapons to inflict harm or coercion, often associated with conflicts or criminal activity.

Culture

The shared beliefs, values, norms, and practices that shape the behavior of people within a group, community, or society.

Related Questions