A Manager Wants to Build 3-Sigma Control Limits for a Process

question 113

Multiple Choice

A manager wants to build 3-sigma control limits for a process. The target value for the mean of the process is 10 units, and the standard deviation of the process is 6. If samples of size 9 are to be taken, the UCL and LCL will be