A Production Line Is to Be Designed to Make 500

question 151

Multiple Choice

A production line is to be designed to make 500 El-More dolls per day. Each doll requires 11 activities totaling 16 minutes of work. The factory operates 750 minutes per day. The required cycle time for this assembly line is