A Production Line Is to Be Designed for a Job

question 137

Multiple Choice

A production line is to be designed for a job with four tasks. The task times are 2.4 minutes, 1.4 minutes, 0.9 minutes, and 1.7 minutes. After line balancing, the largest possible assigned cycle time is ________ and the smallest possible assigned cycle time is ________ minutes.