Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes.
a. Draw the precedence diagram for the set of tasks.
b. Calculate the theoretical minimum number of workstations.
c. Balance this line using the longest task time heuristic.
d. What tasks are assigned to which stations?
e. Does the solution have the minimum number of stations?
Explain.
f. How much idle time is there, summed over all workstations?
g. What is the efficiency of this line?
Single Plantwide
A method used to allocate manufacturing overhead to products, using a single overhead rate for the entire manufacturing plant.
Overhead Rate
The rate at which indirect costs are allocated to produced goods or services, often expressed as a percentage of direct labor or materials cost.
Activity-based Costing
An accounting method that assigns costs to products or services based on the activities they require, improving costing accuracy.
Overhead Cost
Overhead Cost encompasses indirect expenses related to operating a business that are not directly tied to a specific product or service, such as rent, utilities, and administrative salaries.
Q1: Expected output is sometimes referred to as
Q16: Four hundred and eighty minutes of production
Q34: A company is deciding where to
Q41: Which of the following companies use a
Q46: A manufacturing company is considering three
Q49: A production order quantity problem has daily
Q60: Describe the difference between outsourcing and offshoring.
Q73: Labor specialization includes the development of specialized
Q100: A useful tactic for increasing capacity is
Q147: The fixed-position layout would be most appropriate