A firm is planning to set up an assembly line to assemble 40 units per hour, and 57 minutes per hour are productive. The time to perform each task and the tasks which precede each task are:
a. Draw a network diagram of precedence relationships.
b. Compute the required cycle time per unit in minutes.
c. Compute the theoretical minimum number of workstations required to produce 40 units per hour.
d. Balance this line using longest processing time.
e. What is the efficiency of the line obtained in part d?
Tempting
Appealing or attractive, often in a way that makes someone want to do or engage in something impulsively.
Short-Term Reward
Instant gratification or benefits received immediately after completing a task or making a decision, contrasting with long-term rewards.
Neat Freak
An informal term for someone who is obsessively clean or orderly, often going to great lengths to maintain a specific level of tidiness.
Neatness
The quality of being clean, orderly, and tidy.
Q18: Adding a complementary product to what is
Q44: A drawing of the movement of material,
Q45: Managers should seek to control such work
Q74: A product is currently made in a
Q79: Which of the following best describes vertical
Q87: _ is a rapid, low-cost production process
Q95: What are the advantages of shipping by
Q117: All of the following are "opportunities" for
Q138: What is the impact of exchange rates
Q180: _ allowances are those that include the