A Firm's Demand in the Next Four Quarters (Its Aggregate

question 24

Multiple Choice

A firm's demand in the next four quarters (its aggregate planning horizon) is forecast to be 80, 50, 40, and 90 units. Last quarter, the firm produced 60 units. If it uses level scheduling, the firm will.