Each R Requires 2 of Component S and 1 of Part

question 47

Multiple Choice

Each R requires 2 of component S and 1 of part T. The lead time for assembly of R is 3 days. The lead time for the manufacture of S is 5 days. The lead time for the manufacture of T is 10 days. The cumulative lead time for R is __________ days.