Each R Requires 3 of Component S and 3 of Material

question 89

Essay

Each R requires 3 of component S and 3 of material A; each S requires 3 of part T. The lead time for assembly of R is 1 week. The lead time for the manufacture of S is 2 weeks. The lead time for material A is 1 week. The lead time for the procurement of T is 4 weeks.
a. Construct the time-phased product structure.
b. Construct the bill of material.