Examlex

Solved

Consider the Bill of Material for Product J and the Data

question 76

Essay

Consider the bill of material for Product J and the data given in the following table. The gross requirements for J are 200 units in week 6 and 250 units in week 8. Develop the MRP tables for each item for an 8-week planning period. Use the lot-for-lot lot-sizing rule.
 Consider the bill of material for Product J and the data given in the following table. The gross requirements for J are 200 units in week 6 and 250 units in week 8. Develop the MRP tables for each item for an 8-week planning period. Use the lot-for-lot lot-sizing rule.       \begin{array}{|c|c|c|c|} \hline \text { Item } & \text { Lead Time } & \text { Quantity on Hand } & \text { Scheduled receipts } \\ \hline \mathrm{J} & 1 & 0 & \\ \hline \mathrm{K} & 2 & 20 & 30 \mathrm{in} \text { week 2 } \\ \hline \mathrm{L} & 2 & 0 & \\ \hline \mathrm{I} & 1 & 20 & 10 \mathrm{in} \text { week 1 }\\\hline \end{array}
 Item  Lead Time  Quantity on Hand  Scheduled receipts J10K22030in week 2 L20I12010in week 1 \begin{array}{|c|c|c|c|}\hline \text { Item } & \text { Lead Time } & \text { Quantity on Hand } & \text { Scheduled receipts } \\\hline \mathrm{J} & 1 & 0 & \\\hline \mathrm{K} & 2 & 20 & 30 \mathrm{in} \text { week 2 } \\\hline \mathrm{L} & 2 & 0 & \\\hline \mathrm{I} & 1 & 20 & 10 \mathrm{in} \text { week 1 }\\\hline\end{array}


Definitions:

Related Questions