The Jobs Listed Below Needed to Be Completed A) 476 Days
B) 60

question 37

Multiple Choice

The jobs listed below needed to be completed. Assume that it is now day 140. If the jobs are sequenced according to shortest processing time rule, what is the average completion time?
 Job  Processing  Time (days)   Job due date  (days)   A 20180 B 30200 C 10175 D 16230 E 18210\begin{array} { | c | c | c | } \hline \text { Job } & \begin{array} { c } \text { Processing } \\\text { Time (days) }\end{array} & \begin{array} { c } \text { Job due date } \\\text { (days) }\end{array} \\\hline \text { A } & 20 & 180 \\\hline \text { B } & 30 & 200 \\\hline \text { C } & 10 & 175 \\\hline \text { D } & 16 & 230 \\\hline \text { E } & 18 & 210 \\\hline\end{array}


Definitions:

Data Packets

Units of data made into a single package that travels along network paths to its destination.

Access Point

A hardware device that allows wireless devices to connect to a wired network using Wi-Fi, Bluetooth, or similar standards.

Adapter

A hardware or software component that allows one device or application to connect with and work with another, despite differences in format or standards.