Suppose a Given Control Unit Fails, on Average, Every 12,000

question 35

Multiple Choice

Suppose a given control unit fails, on average, every 12,000 hours. It takes an average of 900 hours to repair and reboot this unit. The repair/reboot procedures for this unit are being reconfigured. By how much would average repair/reboot time need to be reduced to increase availability by 5 percent (assuming the control unit's average life remains unchanged) ?


Definitions:

Inventory Levels

The quantity of goods and materials on hand at a particular time within a business, reflecting how well stock is being managed in relation to sales or production demand.

Restocking Costs

Expenses associated with replenishing inventory or stock levels in a business.

Carrying Inventory

The process of holding stock or goods in storage or in transit, with associated costs.

Terms of Sale

The conditions under which a seller will complete a sale, typically specifying the time and method of payment and when the buyer takes possession of the goods.

Related Questions