The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the makespan to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows:  Car  Body Work  (hrs)   Paint  (hrs)   A 102 B 54 C 75 D 36 E 17\begin{array} { c c c } \text { Car } & \begin{array} { c } \text { Body Work } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Paint } \\\text { (hrs) }\end{array} \\\text { A } & 10 & 2 \\\text { B } & 5 & 4 \\\text { C } & 7 & 5 \\\text { D } & 3 & 6 \\\text { E } & 1 & 7\end{array}
Where in the optimum sequence should car E be scheduled?


Definitions:

Ethical Standards

Set of principles that guide moral conduct and decision-making in personal and professional contexts, often reflecting values such as honesty, integrity, and fairness.

Voluntary Turnover

The act of employees leaving an organization by their own choice, as opposed to being dismissed or terminated by the employer.

Facility Closed

The process or state of shutting down operations and ceasing activities in a particular building or location.

Laid Off

It denotes the termination of employment by an employer against the wishes of the employee, often due to economic downturns or company restructuring.

Related Questions