The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:  Job  Processing Time  (hrs)   Due  (hrs from now)   W 44X35Y22Z11\begin{array} { c c c } \text { Job } & \begin{array} { c } \text { Processing Time } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Due } \\\text { (hrs from now) }\end{array} \\\text { W } & 4 & 4 \\\mathrm { X } & 3 & 5 \\\mathrm { Y } & 2 & 2 \\\mathrm { Z } & 1 & 1\end{array}
If he uses the shortest processing time first priority rule to schedule these jobs, what will be the average number of jobs in his shop today?


Definitions:

Similar Associations

Groups or organizations that share common goals, interests, or characteristics.

Institutions

Organizations or complexes of norms and behaviors that are recognized and accepted in society to fulfill collective functions.

Moral Principles

Fundamental beliefs about what is right and wrong that guide ethical decision-making and behavior.

Rawls's Model

A theoretical framework proposed by philosopher John Rawls that emphasizes principles of justice as fairness, including the veil of ignorance and the difference principle.

Related Questions