Consider the portion of a project depicted by this graph: Consider the portion of a project depicted by this graph:   What is the earliest finish time for activity 10-11 (far right-hand side)  if the earliest start time of 8-10 (upper left-hand side)  is 12 and the earliest start time of 9-10 (lower left-hand side)  is 13? A)  22 B)  23 C)  24 D)  25 E)  26
What is the earliest finish time for activity 10-11 (far right-hand side) if the earliest start time of 8-10 (upper left-hand side) is 12 and the earliest start time of 9-10 (lower left-hand side) is 13?