Consider the Following Work Breakdown Structure

question 92

Multiple Choice

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)  time for activity E? A)  91 days B)  99 days C)  100 days D)  101 days E)  115 days
What is the estimated expected (mean) time for activity E?