Consider the Following Work Breakdown Structure

question 50

Multiple Choice

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated slack time for activity D? A)  0 days B)  30 days C)  40 days D)  50 days E)  100 days
What is the estimated slack time for activity D?