Consider the Following Work Breakdown Structure

question 82

Multiple Choice

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the probability that the critical path for this project will be completed within 210 days? A)  0.5000 B)  0.8413 C)  0.9544 D)  0.9772 E)  0.9987
What is the probability that the critical path for this project will be completed within 210 days?