Consider the Following Work Breakdown Structure

question 88

Multiple Choice

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)  time for activity E? A)  31 weeks B)  38 weeks C)  39 weeks D)  40 weeks E)  43 weeks
What is the estimated expected (mean) time for activity E?