If an activity's optimistic time is 4 weeks,its realistic time is 6 weeks,and its pessimistic time is 8 weeks,then its estimated time would be 6 weeks.
Cortana
A digital assistant developed by Microsoft, providing users with voice-command support, reminders, and internet search capabilities.
Blog
A type of website or part of a website that is regularly updated with content, often written in an informal or conversational style.
Typed Notes
Textual notes entered via a keyboard or touchscreen interface, often used for documentation or reminders.
Handwritten Annotations
Personal notes or comments written by hand directly on documents or alongside text in books, often used for clarification, emphasis, or supplementary information.
Q2: Data can move directly from a source
Q16: An extranet is Internet-based communication to support
Q34: This activity focuses on organizing an initial
Q35: Organization enforces reuse practice through policies, resources,
Q49: During project initiation, the focus of developing
Q60: An irreducible part, or an aggregation of
Q90: A schedule of specific IS development projects
Q104: Sources and sinks are internal to the
Q105: During requirements determination, information can be gathered
Q130: Requirements structuring is the first activity of