If an Activity's Optimistic Time Is 4 Weeks,its Realistic Time

question 37

True/False

If an activity's optimistic time is 4 weeks,its realistic time is 6 weeks,and its pessimistic time is 8 weeks,then its estimated time would be 6 weeks.