Definitions:

Crash Cost

The expense associated with reducing the time on a project activity or task, typically higher than normal costs, for faster completion.

Time Savings

The reduction in the amount of time needed to complete a task or activity, often resulting from efficiency improvements or technological advancements.

Activity Duration

The length of time required to complete a specific activity or task.

Crash Duration

The shortest possible time for which an activity or project phase can be scheduled after allocating the maximum amount of resources.