Construct an Activity on the Node (AON) Network Diagram with at Least

question 27

Essay

Construct an Activity on the Node (AON) network diagram with at least 5 tasks that illustrate predecessors, successors and parallel activities.Label the nodes appropriately and assuming your tasks show estimated durations in days, state the estimated time for completing your project.