question 25

Multiple Choice

Corrie contractually agreed to build a house for Ed in exchange for $250 000.After completing about 75 percent of the project,Corrie ran out of resources and informed Ed that she could not continue.She therefore abandoned the job,as well as a substantial amount of materials at the work site.After Corrie left,Ed used the abandoned materials to finish the job himself.Which of the following statements most likely is TRUE?


Definitions:

Related Questions