After reading an article about domain name-related entrepreneurship,you decide to register several domain names for resale.Subsequently,you receive a complaint alleging that you have registered one of those names in bad faith.The complainant has filed for arbitration.The name in question is breadandbutter.com.The complainant,a baker,conducts business under the name.Based on these facts,which of the following statements is most likely to be TRUE?


Definitions:

Crash Cost

The extra expense incurred to reduce the duration of a project, often through the addition of resources or overtime work.

Normal Time

Normal time is a measure of the time required to complete a task or operation under normal working conditions, often used in time and motion studies to set standards and expectations.

Crash Duration

The shortest possible time to complete a task or project phase by allocating maximum resources, often resulting in increased costs.

CPM Network

Critical Path Method Network is a project management tool that identifies key tasks and estimates the shortest completion time for a project by highlighting critical path activities.