Evidence of prior agreements that differ from the written terms of a con?tract can be introduced in court to alter the contract.


Definitions:

Milestone Schedule

A project management tool that outlines significant events or achievements along a project timeline.

Project Risk Management

The process of identifying, analyzing, and responding to project risks to minimize their impact.

Positive Float

The extra time available beyond a project's expected completion time, allowing for delays without affecting the deadline.

Negative Float

In project management, the amount of time by which a project task or activity must be accelerated to meet a deadline or to align with subsequent tasks.