Given W = D * U for an Effort-Driven Task

question 15

Short Answer

Given W = D * U for an effort-driven task. Assume an 8-hour workday. Initially, task R was assigned to Bob. Bob was expected to accomplish 32 hours of work in five days. If Bob were 100 percent available to work on task R during the entire five days, his efficiency rate is __________%.

Assess the development and importance of racial identity theories.
Examine the foundations and criticisms of post-colonial theory.
Evaluate the influence of modern social theories on understanding power dynamics.
Understand the impact of the principal's bankruptcy on the agent's power.

Definitions:

Structure View

An overview representation of a document’s framework, often seen in software to navigate sections or elements of a complex document or website.

Layout View

A feature in database and document software that allows users to see how a document or database form will look when printed or viewed on screen.

Table View

A method of displaying data in rows and columns, similar to a spreadsheet.

Back Up Database

The process of making a copy of database content to protect against data loss.

Related Questions