The tool crib at a large manufacturing company is responsible for providing tools to the factory workers on demand. The tool crib has a variable demand. Historically, its demand has ranged from 340 to 600 small tools per day with an average of 470. Diane, the tool crib attendant, works eight hours a day, five days a week. Each order is for one small tool and each small tool takes Diane 1 minute to retrieve from the bins.
What is the cycle time for an order? (Round the final answer to the first decimal place.)


Definitions:

Work Redesign

The process of altering jobs and work processes to improve employee satisfaction and productivity.

Automation

The shift toward converting work that was traditionally done by hand to being completed by mechanical or electronic devices.

Obsolete

Referring to a product, service, or technology that has become outdated or no longer used, often because it has been replaced by newer alternatives.

Proactive Employers

Organizations or managers who anticipate future challenges or opportunities and act in advance to address them, rather than reacting to events as they happen.

Related Questions