The ____________________,Or the Approved Total Budget for the Project,can Be

question 26

Short Answer

The ____________________,or the approved total budget for the project,can be divided by the cost performance index to calculate the estimate at completion (EAC),which is a forecast of how much the project will cost upon completion.