What Is the Latest That Activity B Can Start If

question 9

Multiple Choice

What is the latest that activity B can start if A is 35 days,B is 5 days,C is 6 days,and D is 7 days long? What is the latest that activity B can start if A is 35 days,B is 5 days,C is 6 days,and D is 7 days long?   A) 35 B) 36 C) 40 D) 41