THE NEXT QUESTIONS ARE BASED ON THE FOLLOWING INFORMATION

question 313

Essay

THE NEXT QUESTIONS ARE BASED ON THE FOLLOWING INFORMATION:
A general contractor has submitted two bids for two projects;A and B.The probability of getting project A is 0.60.The probability of getting project B is 0.75.The probability of getting at least one of the projects is 0.85.
-What is the probability that the contractor will get both projects?