question 36

Multiple Choice

Weston,Inc.,produces widgets.To manufacture a new type of widget,it took 15 iterations before the process reached a steady state of 35 hours.If Weston has an 82% learning rate,use the logarithmic approach to calculate the time it took to manufacture the first widget.