The normal activity duration of Activity X is 5 weeks and is budgeted to cost $12,000.The crash time for this activity is 3 weeks and is expected to cost $32,000.The cost slope for Activity X is calculated as ______.


Definitions:

Intermittent Explosive Disorder

Disorder characterized by (a) several episodes of failure to resist aggressive impulses that result in serious assaultive acts or destruction of property, (b) a degree of aggressiveness grossly out of proportion to the situation, and (c) symptoms not better explained by another mental disorder (such as antisocial personality disorder), the effects of substances, or a medical condition (e.g., a head trauma).

Assault

An act of causing physical harm to someone or attempting or threatening to do so.

Frustration

A psychological state of being upset or annoyed as a result of being unable to change or achieve something.

Intermittent Explosive Disorder

A psychological condition marked by severe episodes of anger that are beyond control and not justified by the circumstances.

Related Questions